Written by Michał Puk, Barrister (adwokat), Supervising Partner, Commercial and Regulatory
Reviewed by Michał Dudkowiak, Barrister (adwokat), Managing Partner
First published: 4 August 2026
Last updated: 6 November 2026
Quick answer
What is CPK Airport and when will it open?
CPK Airport is the new central airport of the Port Polska programme, built between Warsaw and Łódź by the state-owned company Centralny Port Komunikacyjny. Its official opening target is 2032, but the date is not guaranteed: in November 2026 the building permit is still pending and is expected in December 2026, after the final environmental decision announced at the end of December 2025 and consent for preparatory works in October 2026.
The largest contract, the passenger terminal worth more than PLN 5 billion, has passed the competitive dialogue stage; four consortia remain and tenders are due on 9 December 2026. For foreign contractors the first question is eligibility: since 9 September 2025 companies from countries without a procurement agreement with the EU have no guaranteed right to take part in Polish tenders.
2032
official opening target – under review until the end of 2026
34 million
passengers a year in the first phase, expandable to 44 million
PLN 54 bn+
CPK procedures launched and planned for 2026 – planned values
PLN 5 bn+
terminal contract – four consortia left in the tender
Public procurement for CPK and Port Polska tenders
Eligibility checks, tender documents, consortium and subcontract agreements, appeals to the National Appeal Chamber and the performance of the contract – a One Stop Shop for foreign companies bidding in Poland.
We reply within 24 hours with a scope and a timeline.
Part of the Public Procurement practice
Dudkowiak & Putyra’s public procurement practice acts for foreign contractors as a one-stop shop: procurement, contracts, a Polish company or branch, tax and work permits for site staff. See our public procurement lawyers for foreign contractors in Poland.
CPK Airport in Poland – key facts
The figures most often asked about, with the state on 6 November 2026. Project values are CPK’s plans, not awarded contracts.
THE PROJECT
Opening
2032 – official target
The tender documents require the terminal contract to be performed by 15 November 2032; intermediate deadlines follow from the functional and utility programme and the contract. The new management is reviewing the schedule until the end of 2026.
Building permit
Expected December 2026
Final environmental decision announced at the end of December 2025; consent for preparatory works at the end of October 2026. The main building permit has not yet been issued.
Terminal
400,000–450,000 m²
Figures differ between CPK documents. 34 million passengers a year at opening, expandable to 44 million; terminal, railway station and bus terminal under one roof.
Terminal tender
4 consortia
Competitive dialogue completed. After several extensions, tenders are due on 9 December 2026 at 12:00 and will be opened at 12:10; tenders must remain valid until 7 April 2027.
2026 pipeline
PLN 54 bn+ planned
In August 2026 CPK announced 58 new procedures worth over PLN 40 billion for the rest of 2026; with procedures already launched the total exceeds PLN 54 billion.
RULES FOR CONTRACTORS
EU threshold for works
EUR 5,404,000
From 1 January 2026, for both classic and sectoral contracting entities.
Bidders from non-agreement third countries
No guaranteed access
Since 9 September 2025, contractors from countries without a procurement agreement with the EU may take part only where the tender documents allow it.
Subcontractors
Paid within 30 days
Maximum payment term in a subcontract, counted from delivery of the invoice or bill confirming the subcontracted work (Article 464(2) Pzp).
Price indexation
Contracts over 6 months
Works and services contracts concluded for more than six months must contain indexation clauses (Article 439 Pzp) – a clause, not an automatic increase.
Appeals to KIO
10 days
In above-threshold procedures where the decision is sent electronically; 15 days where it is sent by other means.
CPK timeline and project milestones: where Port Polska stands in November 2026
Most of what was announced for 2025 has happened; the step that decides the pace of 2027 – the main building permit – has not. The list separates what is done from what is still planned.
PORT POLSKA · STATUS ON 6 NOVEMBER 2026
May – August 2025
CPK opens the competitive dialogue for the passenger terminal; five consortia of 16 companies, 14 of them Polish, apply. In July 2025 the National Appeal Chamber upholds the revenue requirement, the limit of five contractors and the selection criteria.
December 2025
The dialogue with the five consortia begins. At the end of December 2025 CPK announces the final environmental decision for the airport, the railway junction, the road access and the related infrastructure.
February – June 2026
Six tenders are submitted for the deep foundations of the terminal; Budimex wins and signs a contract worth about PLN 146 million gross for more than 8,000 piles and columns, due for completion at the turn of 2027 and 2028.
3 July 2026
CPK invites the five consortia to submit priced tenders for the terminal.
August – September 2026
The PORR – Doraco consortium appeals to the National Appeal Chamber against the tender documents in August 2026.
October – November 2026
On 7 October 2026 the Polimex Mostostal – Hochtief consortium withdraws, leaving four. CPK receives consent for preparatory works, and on 30 October 2026 a new chief executive is appointed to assess the project by the end of 2026. On 30 October 2026 CPK moves the tender deadline – after 1 September, 1 October, 30 October and 9 November – to 9 December 2026; no tenders have been opened yet.
December 2026 – planned
Building permit for the airport.
9 December 2026 – planned
Submission and opening of tenders for the terminal; tenders remain valid until 7 April 2027.
After the evaluation – planned
Contract with the general contractor of the terminal.
2032 – target
Terminal contract to be performed by 15 November 2032 under the tender documents; 2032 is also CPK’s official opening target.
What this means for planning: the main foundation works and the terminal construction depend on the building permit. Treat 2032 as the official target, not as a fixed date, until CPK publishes the outcome of the schedule review.
What is the CPK airport project?
Port Polska is the current name of the programme formerly presented in English as the Solidarity Transport Hub. It combines a new central airport with a high-speed rail network and road links. The investor is Centralny Port Komunikacyjny sp. z o.o. (CPK), a company wholly owned by the State Treasury.
The airport is being built between Warsaw and Łódź, in the municipalities of Baranów, Wiskitki and Teresin in the Mazovia region. Its core is a passenger terminal of 400,000–450,000 m² (figures differ between CPK documents), designed by Foster + Partners, with the main railway station and the bus terminal under one roof. The high-speed “Y” line is to connect the airport with Warsaw and Łódź first, and later with Poznań and Wrocław.
The programme also covers a freight area (Cargo City) and a business district next to the airport (Airport City), which matter for investors in Poland looking at logistics and services rather than construction.
Phased construction and modular airport infrastructure
The airport is planned in phases. The first phase is to include a terminal for 34 million passengers a year and an underground railway station integrated with the terminal. The terminal tender was drafted so that capacity can be increased to 44 million passengers if traffic requires it – for contractors this means change and extension mechanisms built into the contracts rather than a single fixed scope.
CPK tenders and competitive dialogue in practice
CPK awards its contracts under the Polish Public Procurement Law of 11 September 2019 (Pzp), which implements the EU procurement directives. Above the EU thresholds – for works EUR 5,404,000 from 1 January 2026 – notices are also published in the EU’s Tenders Electronic Daily (TED).
The pipeline. In August 2026 CPK announced 58 new procedures worth over PLN 40 billion for the rest of 2026. Together with the procedures already launched this year, the total exceeds PLN 54 billion. These are CPK’s planned values, not awarded tenders or signed contracts, and they may have changed since.
| Procedure | How it works | Used in Port Polska for |
|---|---|---|
| Competitive dialogue | Prequalification, then dialogue with a shortlist, then final priced tenders | Passenger terminal, baggage handling system, passenger boarding bridges |
| Framework agreement and call-off | A group of pre-selected firms competes for individual orders | Deep foundations of the terminal – nine firms invited, six tenders |
| Open and restricted procedures | Single-stage or two-stage tender without negotiation | Standard works, supplies and services |
| Negotiated procedures | Negotiation of tenders with admitted contractors | Specialist consultancy and works where the scope cannot be fixed in advance |
Examples from procedures reported by CPK in 2025–2026. The procedure for a given contract is stated in its notice.
For the rules beyond CPK, see our guide to public procurement regulation in Poland.
How competitive dialogue works in CPK projects
The terminal tender shows the whole sequence. CPK published the notice in May 2025 and limited the dialogue to a maximum of five contractors. After prequalification it held a dialogue with five consortia from December 2025, during which the contractors commented on the documents, the contract terms and the evaluation rules. On 3 July 2026 CPK invited them to submit priced tenders, initially by 1 September 2026. The deadline was then moved to 1 October, 30 October and 9 November and, by an amendment of 30 October 2026, to 9 December 2026 at 12:00, with the opening at 12:10; tenders must remain valid until 7 April 2027.
Tenders are evaluated on price (75 points), the technology and organisation of works (20 points) and the warranty terms (5 points); within the quality criterion, 7.47 points concern the supply chain and the country of origin of products under the EU Customs Code. No tender security (wadium) is required in the terminal tender, but a performance security is. The invited contractors may not form new consortia – neither with companies outside the procedure nor among themselves. The remaining consortia are led by Mirbud, Budimex (with Strabag), NDI (with BESIX) and PORR (with Doraco).

Participation conditions in the terminal tender
| Condition | Requirement | Stage |
|---|---|---|
| Annual revenue | At least PLN 4 billion in each of the last four years – one contractor, or the sum of consortium members | Prequalification, 2025 |
| Revenue of one consortium member | At least PLN 1 billion (lowered from PLN 2 billion) | Prequalification, 2025 |
| Experience | Two works of at least PLN 200 million net each in the last 15 years (lowered from PLN 300 million) | Prequalification, 2025 |
| Selection criterion no. 1 | Reference threshold lowered from PLN 300 million to PLN 200 million | Selection for the dialogue, 2025 |
| Ranking for the shortlist | Points for buildings in the EU and EFTA over PLN 200 million each, passenger terminals in Poland over PLN 50 million and passenger terminals worldwide over PLN 1 billion | Selection for the dialogue, 2025 |
| Number admitted | Up to five contractors | Selection for the dialogue, 2025 |
Conditions of the terminal tender only (prequalification and tender rules, Part VI). CPK lowered the thresholds by a modification of 17 June 2025; in its judgment of 21 July 2025 (KIO 2312/25, KIO 2313/25, KIO 2342/25, KIO 2363/25) the National Appeal Chamber upheld the PLN 4 billion revenue requirement, the limit of five contractors and the selection criteria. Other CPK tenders set their own conditions.
Can foreign companies bid for CPK tenders?
Yes, but where the company comes from now matters. Following the judgments of the Court of Justice of the EU in Kolin (C-652/22, 22 October 2024) and CRRC Qingdao Sifang (13 March 2025), an amendment to the Pzp in force since 9 September 2025 (Articles 16a and 16b Pzp) gives, in practice, three groups of contractors.
EU and EEA
Equal treatment with Polish contractors.
FULL ACCESS AND REMEDIES
Countries with a procurement agreement with the EU
Parties to the WTO Government Procurement Agreement (GPA) and to other EU agreements covering procurement are treated equally within the scope of those agreements.
CHECK THE SCOPE OF THE AGREEMENT
Other third countries
No guaranteed right to take part. The contracting authority may admit them, but only where the notice or the tender documents expressly say so.
READ EACH TENDER’S DOCUMENTS
Without such a clause in the documents, contractors from other third countries have no access. The rule is not limited to the bidder: the tender documents also decide whether such companies may act as consortium members, as entities lending their capacity or as subcontractors. A consortium with a non-admitted member has its request or tender rejected, while an entity lending capacity must be replaced. The terminal tender admits only contractors established in the EU, the EEA, a GPA party or a country with an EU procurement agreement, and the restriction also covers consortium members, entities lending capacity and subcontractors – but not suppliers of materials, machinery and equipment (prequalification and tender rules, Part V points 9–13). In procedures started on or after 9 September 2025, contractors from countries not covered by an agreement cannot appeal to the National Appeal Chamber; procedures started earlier, including the terminal tender, follow the transitional rules of the amending act (Articles 3 and 4).
Before a foreign company prices a CPK tender, it should check one line in the tender documents: whether contractors from its country are admitted at all.

Foreign subsidies (FSR)
Under Article 28 of Regulation (EU) 2022/2560 a bidder must notify foreign financial contributions where the estimated value of the contract is at least EUR 250 million and, in addition, the bidder – together with its group and its main subcontractors and suppliers – has received foreign financial contributions of at least EUR 4 million per third country in the three years before notification. Below that threshold the bidder submits a declaration instead. Where a contract is divided into lots, the lots applied for must also be worth at least EUR 125 million. The terminal contract is not divided into lots and meets the value condition; it requires one form per consortium, and a main subcontractor or supplier is one with a share of more than 20% of the tender value.
Sanctions
EU law prohibits awarding public contracts to Russian nationals, to entities established in Russia, to entities more than 50% owned by them and to entities acting on their behalf or at their direction, including where they account for more than 10% of the contract value as subcontractors, suppliers or entities whose capacity is relied on. Polish law adds exclusion of persons and entities on the national sanctions list (Article 7(1) of the Act of 13 April 2022); awarding a contract with an excluded entity is punishable by a fine of up to PLN 20 million. Our guide to economic sanctions in Poland explains the lists.
Do you need a Polish company?
The Pzp does not make a Polish company a condition of bidding, provided the company is established in a country the tender admits and submits documents in Polish or with a Polish translation. Foreign contractors usually enter CPK tenders through a consortium formed before the request to participate. Performing a contract in Poland raises separate questions: a branch in Poland or a subsidiary, tax registration and work permits for site staff.
CPK project conditions and requirements for contractors
Beyond the participation conditions of each tender, CPK applies contract terms and policies that affect pricing and the choice of partners.
Sustainability, BIM and ESG requirements in CPK
CPK’s communications and tender documents emphasise low-carbon construction, BIM-based design and documentation for major structures, and its Code of Contractor Conduct. CPK has also signed an agreement with the state development bank BGK on strengthening the participation of Polish firms in Port Polska supply chains, which explains the weight of Polish partners in the consortia.
Price indexation
Works and services contracts concluded for more than six months must contain indexation clauses setting how the remuneration changes when the cost of performance changes (Article 439 Pzp). The clause gives a mechanism agreed in the contract – its thresholds, index and cap – not an automatic right to a higher price.
Legal and compliance requirements for CPK contractors
- Exclusion grounds. The mandatory and optional grounds of the Pzp – such as certain criminal convictions, tax and social security arrears, insolvency or serious professional misconduct – apply to every consortium member and to entities lending capacity.
- European Single Procurement Document (ESPD). In above-threshold procedures the contractor first confirms in the ESPD that it is not excluded and meets the conditions; the supporting documents follow on request. In two-stage procedures the ESPD is submitted with the request to participate, and each consortium member and entity lending capacity submits its own.
- Cybersecurity. Under the National Cybersecurity System Act a tender may not include ICT products from suppliers designated as high-risk; the terminal tender makes this a ground for rejection.
- Code of Contractor Conduct. CPK’s own rules on ethics, anti-corruption and fair competition, applied in its procedures and contracts.
- Voluntary certification. From 12 July 2026 contractors may obtain a certificate confirming that they are not excluded and meet selected conditions. It is optional and does not replace the documents a tender requires; capability levels for works are to apply from 1 January 2027.
CPK tender readiness checklist: is your company ready to bid?
Nine categories to check before you commit to a CPK tender. Choose your role – bidder, consortium member or subcontractor – and tick off each category once you have checked it against the tender documents. Your ticks stay in this browser, and you can print the list or save it as PDF.
CPK TENDER READINESS CHECKLIST
Is your company ready to take part in a CPK tender?
Your role in the tender
Categories to check, not a list of documents. The exact requirements, forms and deadlines are set by the notice and the tender documents (SWZ) of each procedure, and they differ between CPK tenders.
-
Where to check: the notice and the tender documents (SWZ). On this page: Can foreign companies bid?
-
Where to check: the notice and the tender documents (SWZ). On this page: Legal and compliance requirements
-
Where to check: the conditions and the list of required documents in the tender documents. On this page: Conditions in the terminal tender
-
Where to check: the tender documents (SWZ) and the notice. On this page: Legal and compliance requirements
-
Where to check: the tender documents (SWZ) and the forms of statements. On this page: Sanctions
-
Where to check: the notice and the tender documents (SWZ). On this page: Foreign subsidies (FSR)
-
Where to check: the tender documents (SWZ) and the draft contract. On this page: Subcontractors in CPK projects
-
Where to check: the tender documents (SWZ) and the draft contract. On this page: Project conditions and requirements
-
Where to check: the notice, the tender documents (SWZ) and the e-procurement platform. On this page: KIO appeals
0 of 9 checked
Subcontractors in CPK projects: rules, roles and opportunities
With 14 of the 16 companies in the terminal tender being Polish, the realistic route into Port Polska for many foreign firms is a role in a consortium formed at the start of a procedure, or as a subcontractor or supplier of a specialist system. In the terminal tender no new consortia may be formed at this stage, so the route there is subcontracting or supply. The main contractor remains responsible to CPK for the whole contract.

Legal framework for subcontracting in CPK
- Penalties and payment terms (Article 463 Pzp). A subcontract may not impose contractual penalties beyond those in the main contract, and its conditions and terms of payment may not be less favourable than those agreed between CPK and the contractor. The provision covers these terms, not every clause of the subcontract.
- Payment within 30 days (Article 464(2) Pzp). In a works contract, the payment term in any subcontract may not exceed 30 days from delivery to the contractor of the invoice or bill confirming performance of the subcontracted works, supplies or services.
- Submission to CPK (Article 464 Pzp). In works contracts the draft subcontract for works and its amendments are submitted to the contracting authority, which may object within the period set in the main contract; no objection means acceptance. A copy of the signed subcontract follows within 7 days, and copies of supply and service subcontracts are also submitted.
- Exclusion checks of subcontractors (Article 462(5) Pzp). Subcontractors are checked for exclusion grounds only where the procurement documents provide for it; in the terminal tender CPK checks selected mandatory and optional grounds.
- Direct payment (Article 465 Pzp). Where the contractor fails to pay, the contracting authority may pay the subcontractor directly – only the remuneration due, without interest, under an accepted works subcontract or a submitted supply or service subcontract – and deduct it from the contractor’s remuneration. The contractor has at least 7 days to comment, and repeated direct payments or payments above 5% of the contract value entitle the authority to withdraw from the contract.
Types of subcontractors in airport infrastructure projects
Specialist technical subcontractors (MEP, baggage handling, security screening, airfield systems, rail signalling), local construction firms for earthworks and foundations, and support services such as logistics, temporary works and environmental monitoring. Some systems – baggage handling or boarding bridges – are procured by CPK separately, so suppliers may bid directly rather than through the terminal contractor.
Strategic opportunities for subcontractors in CPK
Because the large contracts are design-and-build, subcontractors are often lined up during tender preparation through letters of intent or framework agreements with the consortia. Being ready means documents in order for the exclusion and capacity checks, BIM-compatible workflows and a clear answer to the third-country rule if any part of the supply chain comes from outside the EU. We draft and negotiate these consortium and subcontract agreements.
For most foreign firms the realistic way into Port Polska is a role in a consortium formed at the start of a procedure, or as a subcontractor or supplier of a specialist system – not a bid of their own.
KIO appeals in CPK tenders: deadlines and fees
Disputes in CPK procedures go to the National Appeal Chamber (Krajowa Izba Odwoławcza, KIO). A complaint against a KIO judgment is filed within 14 days of its delivery with the Regional Court in Warsaw, the public procurement court. The terminal tender has already produced appeals against the participation conditions in 2025 and against the tender documents in 2026.
APPEALS TO THE NATIONAL APPEAL CHAMBER
Deadline
10 days
In above-threshold procedures, from the day the decision was sent electronically, or 15 days if sent by other means; against the notice and the tender documents, from publication in the Official Journal of the EU or from making the documents available. Shorter deadlines apply below the thresholds, and deadlines are counted under the Civil Code.
Fee
PLN 20,000
Entry fee for an appeal in an above-threshold works procedure, including sectoral contracts.
Contractors from non-agreement third countries
No appeal
In procedures started on or after 9 September 2025; the terminal tender, started earlier, follows the transitional rules.
Since 13 March 2026
New KIO rules
Remote hearings and preclusion of evidence apply to appeals in procedures started on or after 13 March 2026, not automatically to the terminal tender started in 2025.
In CPK tenders the time to challenge the tender documents is counted in days, not weeks – a contractor that sees a condition it cannot meet should decide on an appeal while it is still reading the documents.
CPK tenders in Poland – 3 compliance requirements
Anna Szymielewicz, Attorney (radca prawny), Partner, on the digital, sustainability and ethical requirements that international contractors meet in CPK tenders on top of financial and technical capacity.
FROM OUR AVIATION TEAM · FREE GUIDE (PDF)
Air passenger claims in Poland – a guide for air carriers
Complaints, the Passenger Rights Ombudsman and court proceedings: deadlines, burden of proof, court fees and jurisdiction in Regulation 261/2004 cases – with cases from our practice. As of 2 November 2026.
How to track CPK tenders and investment opportunities
- portpolska.pl. CPK’s official website with the procurement plan, links to current notices and the Code of Contractor Conduct: portpolska.pl.
- TED. Above-threshold notices in the EU’s Tenders Electronic Daily: ted.europa.eu.
- The tender documents. The only place that says whether third-country contractors, consortium members or subcontractors are admitted in a given procedure.
News portals report on CPK quickly, but dates and values should be checked against CPK’s own announcements before they go into a bid.
Send us the tender, your country of registration and your planned role.
Polish lawyers do not publish fee rates; we reply within 24 hours with a scope and a fee proposal.

Barrister (adwokat), Supervising Partner, Commercial and Regulatory
Author
Entered on the list of advocates of the Poznań Bar Association on 28 May 2018; law at Adam Mickiewicz University in Poznań. Supervises Dudkowiak & Putyra’s commercial and regulatory practice, which includes public procurement: for contractors in CPK and other public tenders he reviews the tender documents and contract terms and drafts consortium, subcontract and supply agreements. His regulatory work covers Polish and EU sanctions assessments and payment-delay proceedings before the competition authority for a supplier to the railway industry.

Barrister (adwokat), Managing Partner, Head of Foreign Investment
Reviewer
Entered on the list of advocates of the Zielona Góra Bar Association on 17 October 2013; law at Adam Mickiewicz University in Poznań and a Diploma in British and EU Law from the University of Cambridge. Managing Partner and head of Dudkowiak & Putyra’s foreign investment practice, he advises foreign groups entering Poland on the form of their presence – a branch or a subsidiary – and on M&A and competition clearance. He served on the audit committee of an internal investigation into an infrastructure project carried out abroad by a Polish construction group.

Attorney (radca prawny), Partner, Head of Litigation and Arbitration
Expert in the video
Admitted as an attorney-at-law in 2017; law at Adam Mickiewicz University in Poznań. Heads Dudkowiak & Putyra’s litigation and arbitration practice – commercial disputes before Polish courts and arbitral tribunals, including transport and aviation claims, and the negotiation of settlements. In the video on this page she explains the compliance requirements international contractors meet in CPK tenders.
Read more
Aviation law in Poland | Public procurement regulation | Defence procurement and offset | Foreign investment control | Economic sanctions | Branch in Poland
Sources and methodology
Legal basis. Act of 11 September 2019 – Public Procurement Law (Prawo zamówień publicznych, Pzp), consolidated text Journal of Laws 2026, item 793 (state of the law on 25 May 2026), in particular Articles 439 (indexation) and 463–465 (subcontracting) and the provisions on appeals; Act of 9 July 2025 amending the Pzp (Journal of Laws 2025, item 1165) on contractors from third countries, in force since 9 September 2025; Articles 3 and 4 of that act (transitional rules); Act of 21 May 2025 (Journal of Laws 2025, item 769) on the KIO rules applicable from 13 March 2026; Act on the certification of public procurement contractors (Journal of Laws 2025, item 1235); Regulation of the Prime Minister of 30 December 2020 on appeal fees (Journal of Laws 2020, item 2437); judgments of the Court of Justice of the EU of 22 October 2024 in Kolin (C-652/22) and of 13 March 2025 in CRRC Qingdao Sifang; Commission Delegated Regulations of October 2025 amending the thresholds of Directives 2014/24/EU and 2014/25/EU, applicable from 1 January 2026; Regulation (EU) 2022/2560 on foreign subsidies, with the Commission guidelines of 9 January 2026 and its first review of 14 July 2026; Council Regulation (EU) No 833/2014, Article 5k, as amended, including by Regulation (EU) 2025/2033; Act of 13 April 2022 on special solutions to counteract support for aggression against Ukraine. Texts: ISAP, EUR-Lex.
Terminal tender. Prequalification and tender rules (OPW) and terms of reference (SWZ) of the passenger terminal procedure, including the amendment of 30 October 2026; KIO judgment of 21 July 2025 (KIO 2312/25, KIO 2313/25, KIO 2342/25, KIO 2363/25). The draft contract is confidential and was not reviewed.
Project facts. Announcements of Centralny Port Komunikacyjny sp. z o.o. as reported by: Sektorkolejowy.pl, 13 October 2026; TransInfo, 12 October 2026; WNP.pl, November 2026; Pasazer.com, 21 July 2025 (KIO judgment on the terminal conditions); Rzeczpospolita, November 2026 (preparatory works, building permit, new management); PAP Biznes (environmental decision); PropertyNews.pl (procurement plan for 2026). Tender values for 2026 are CPK’s planned figures, not awarded tenders or signed contracts; 2032 is CPK’s official opening target and is under review.
State of the law and facts: 6 November 2026. This page is general information, not legal advice; eligibility and conditions are set by the documents of each procedure.
Corrections: 6 November 2026, after legal review – date of the environmental decision, completion date under the tender documents, tender deadline, conditions of the terminal tender, third-country, sanctions and FSR rules, appeal deadlines; unconfirmed details (runways, company formation date, trial piling) removed.
FAQ – CPK Airport and CPK tenders
When will CPK Airport open?
The official target is 2032 and the tender documents require the terminal contract to be performed by 15 November 2032, but the new CPK management is reviewing the schedule until the end of 2026, so the date is not guaranteed.
Where is CPK Airport located?
Between Warsaw and Łódź, in the municipalities of Baranów, Wiskitki and Teresin in the Mazovia region of Poland.
What is Port Polska?
Port Polska is the current name of the CPK programme – a new central airport, a high-speed rail network and road links – run by the state-owned company Centralny Port Komunikacyjny sp. z o.o. and formerly presented in English as the Solidarity Transport Hub.
Has construction of CPK Airport started?
Preparatory works and trial piling have been carried out, but the main building permit for the airport is expected only in December 2026, and the main foundation and terminal works depend on it.
Who is bidding for the CPK passenger terminal?
After the Polimex Mostostal – Hochtief consortium withdrew on 7 October 2026, four consortia remain, led by Mirbud, Budimex (with Strabag), NDI (with BESIX) and PORR (with Doraco); tenders are due on 9 December 2026.
How much is CPK tendering in 2026?
According to its announcement of August 2026, CPK plans 58 new procedures worth over PLN 40 billion for the rest of 2026 and, with those already launched, more than PLN 54 billion in total – planned values, not awarded contracts.
Can a company from outside the EU bid for CPK tenders?
A company from a country covered by the WTO GPA or another EU procurement agreement is treated equally within that agreement; a company from any other country has no guaranteed right to bid and may take part only where the tender documents expressly allow it.
Do I need a Polish company to bid for a CPK tender?
No, a Polish company is not a condition of bidding under the Pzp if your company is established in a country the tender admits and submits documents in Polish or with a translation, but performing the contract may require a branch or subsidiary, tax registration and work permits for staff, which are best planned before the bid.
What is competitive dialogue in CPK tenders?
A procedure in which CPK prequalifies contractors, discusses the solution and the contract terms with a shortlist and then asks for final priced tenders; CPK used it for the passenger terminal, the baggage handling system and the boarding bridges.
How quickly must a CPK subcontractor be paid?
The payment term in a subcontract under a public contract may not exceed 30 days from delivery of the invoice or bill confirming the subcontracted work (Article 464(2) Pzp), and the contracting authority may pay an accepted subcontractor directly if the contractor fails to pay.
How long do I have to appeal in a CPK tender?
In above-threshold procedures the deadline is 10 days from the electronic notice of the decision (15 days if sent by other means), and the entry fee for an appeal in a works procedure is PLN 20,000.
Does the Foreign Subsidies Regulation apply to CPK tenders?
Notification is required where the contract is worth at least EUR 250 million (EUR 125 million for the lots applied for in a contract divided into lots) and the bidder, with its group and main subcontractors and suppliers, received at least EUR 4 million from one third country in the previous three years; below that, a declaration is submitted.
